Decision made: Pumped storage plant in Happurg to be recommissioned
Pumped storage operations have been suspended since 2011 as a precautionary measure due to localized damage to the base of the upper reservoir. Since then, intensive investigations of the subsoil have been carried out, geotechnical assessments have been prepared, and various approaches to remediation have been examined. Based on the findings, a technical concept for upgrading the upper reservoir has been developed and refined, enabling it to be recommissioned in a cost-effective manner. The responsible licensing authority, the Nürnberger Land District Office, has approved this concept as part of a planning approval procedure. The plant technology in the powerhouse will also be repaired as part of the overall project. Commissioning is scheduled for 2028.
Documents (GER only)
BR report of 9 April 2026
BR report on the Happurg pumped storage plant (GER)
Impressions
17 June 2026
|
|
|
| In the upper basin: Preparation of the subgrade with approximately 17,000 vibro-compacted columns has been completed, the barrier layers have been applied almost across the entire area, and the test section for the final asphalting has already been prepared. | |
|
|
|
April 2026
|
|
|
|
|
September 2025
|
|
|
|
|
|
|
June 2025
|
|
March 2025
October 2024
|
|
|
Images (c) Josef Rädlinger Unternehmensgruppe